聚力“六個主題年” | 工程建設集團S465四川米易縣項目取得新進展
近(jin)日,工程(cheng)建(jian)設集團S465四(si)川米易縣項(xiang)目主線K0+100-K4+956段瀝青攤鋪順利完成(cheng),項目進入全(quan)面沖(chong)刺收尾階段。
此次瀝青攤鋪道(dao)路全長4.85公里,設計厚度10厘米,設計寬度(du)10.5米。施(shi)工(gong)(gong)前,項(xiang)目部召開施(shi)工(gong)(gong)專題會,重點對現場(chang)安全(quan)管控(kong)(kong)(kong)、攤鋪(pu)(pu)(pu)(pu)工(gong)(gong)藝流程、技術控(kong)(kong)(kong)制要點和施(shi)工(gong)(gong)規范要求(qiu)進行詳(xiang)細(xi)交底。施(shi)工(gong)(gong)過程中,現場(chang)技術人員全(quan)程盯控(kong)(kong)(kong),嚴格控(kong)(kong)(kong)制攤鋪(pu)(pu)(pu)(pu)速(su)度、攤鋪(pu)(pu)(pu)(pu)厚度、碾壓工(gong)(gong)藝、路面平(ping)整度等關鍵(jian)工(gong)(gong)序,確保了(le)攤鋪(pu)(pu)(pu)(pu)任務(wu)優(you)質高效完成(cheng)。
下一步(bu),S465四川米(mi)易縣項(xiang)目將繼(ji)續發揚(yang)“拼(pin)搏進取、敢打硬仗”的奮斗精神,加強現場管理,錨定節點(dian)目標,決戰四季度,確保按期完成通(tong)車任務。